In which ADM phase is an Architecture Contract developed to cover the overall implementation and deployment process?

Study for the TOGAF Level 1 Test with targeted multiple-choice questions. Each query includes in-depth hints and explanations to help you understand core concepts. Prepare effortlessly and excel in your TOGAF certification exam!

The Architecture Contract is developed in Phase G, which is also known as the Implementation Governance phase of the TOGAF Architecture Development Method (ADM). During this phase, the primary focus is on ensuring that the architecture is implemented correctly and that the project adheres to the established architecture principles, guidelines, and standards.

The Architecture Contract serves as a formal agreement between the various stakeholders involved in the implementation process, detailing how the architecture will be executed and governed. This includes defining the roles, responsibilities, and deliverables for both the project team and the stakeholders, ensuring that there is clarity throughout the deployment process.

Furthermore, Phase G emphasizes the importance of monitoring and controlling the architecture and its implementation. The Architecture Contract supports this by setting specific expectations and outlining how compliance will be managed, enabling effective governance throughout the project lifecycle.

This detailed contractual framework is crucial for mitigating risks and aligning the implementation with the originally intended architecture, ultimately leading to a successful deployment.